Overview

The Northeast Omaha High Rate Treatment Basin (NEOHRTB) is a critical infrastructure investment designed to address high-volume outfalls along the Missouri River and enhance water quality in the Minne Lusa and Burt-Izard basins in Northwest Omaha. 


This project directly supports the City’s obligation to meet the 85% combined sewer overflow (CSO) volume capture requirement outlined in the EPA’s CSO Control Policy Consent Order.
Identified in the 2021 CSO Long Term Control Plan Update as a key alternative to the Deep Tunnel, the NEOHRTB will include four diversion structures, shallow conveyance sewers, grit and screening facilities, a deep conveyance sewer and a high-rate treatment basin located north of Abbott Drive between 6th and 11th Streets, near the Omaha Levee. 

Schedule

KIC_NEORHTB_ConstPkgSchedule-OptionA_20251223.png

What to Expect

Check back in the future for additional updates.

water icon

Upcoming Events

The project does not include any public participation events. Public and stakeholder outreach will be managed through the distribution of construction notices and updates via flyers and emails to residents, businesses, and property owners. Individual stakeholder meetings are being held as requested to further discuss the project details, anticipated construction schedule, traffic restrictions during construction, and access to properties.

Past Events

There are no past events.

Resources

Contact

 

City of Omaha
Public Works Department
Josh Dodson
402-444-3915
 
Consultant
Wade Trim
Stephen D’Alecy
Construction Manager
402-885-7675